Hope Manor II Update #9
Hope Manor II Update #9
25-Apr-2014
Current Project Update #9:
We are continuing to make excellent progress on Volunteer of America’s Hope Manor II apartments. We are finishing the masonry on the outside of the building and the flexicore installation is complete. The piping and electrical installation, as well as the plumbing main, vents and drains are coming along as per schedule. While the HVAC vertical water risers are nearly installed through out the building. Finally, we have begun framing the soffits and ceiling on the first floor.